From submittal to CO. Five phases. No surprises.

Every Cleared project follows the same documented workflow under Florida Statute 553.791. Here is exactly what to expect and when.

  1. 01 · Day 0

    Intake

    Upload drawings, structural calcs, energy compliance, and product approvals into the Cleared portal. We confirm scope within 4 business hours and issue a fixed-fee proposal.

    Signed agreement · Project number · Reviewer assigned
  2. 02 · Day 1–7

    Plan Review

    A licensed Florida engineer or architect performs a full code review against the Florida Building Code 8th Edition. Comments are returned on the original set with cloud markups and a tracked correction log.

    Red-lined set · Correction log · Compliance summary
  3. 03 · Day 7–10

    Affidavit & Permit

    Once revisions clear, we sign and file the Private Provider Affidavit with the AHJ. By statute, the building department has 30 business days but typically issues the permit within a week.

    FS 553.791 affidavit · Permit issued
  4. 04 · Construction

    Inspections

    Your super requests inspections through the portal — same- or next-day scheduling. Our inspectors meet your crews on site, document the work, and deliver digital reports within two hours.

    Digital inspection reports · Photo records
  5. 05 · Close-out

    Certificate of Occupancy

    Final inspection, threshold sign-off, and submittal of the Private Provider close-out package to the AHJ. All records remain available in the portal for the life of the building.

    CO support · Archived project file